Water, Power and Fuel |
 |
Water
Requirement
The
Water requirement will be about 26 MGD
Strategy: The project location being with in 5 kms from
Godavari River the required water will be drawn from the
Godavari River.
Power Requirement:
The
Power requirement will be 35 MW Consumption, A power station of
40 MW capacity is considered for the project.
Strategy:
The Power requirement would be met 80% by captive power
generation and the remaining 20% from Grid or as per the Policy
stipulations of the State Government.
Fuel Requirement:
Two types of
fuels are required for the project, viz.,. Coal and Furnace
Oil. Coal
requirement would be about 600 to 700 TPD
Furnace oil
requirement will be 24 M3 per day
Alternative
Strategy: If Natural Gas pipeline of ONGC passes through at
a distance of 10 KMs from the proposed location |